Design & Engineering
6 Project Management.png

Project Management

Producing detailed shop drawings, bill of quantities / materials, work scheduling (PERT / CPM with S-Curve), progress reports, coordinating with general contractors and subcontractors to deliver projects on time and according to the vision of its designer.

Producing detailed shop drawings, physical accomplishment reports, project timeline (Gantt Chart), work scheduling (PERT / CPM with S-Curve), and progress reports using a combination of licensed versions of Microsoft Office software such as Microsoft Excel, Microsoft PowerPoint and Microsoft Project, coordinating with contractors, consultants and suppliers to deliver projects on time and according to the vision of its designer.


ON Semiconductor Head Office

Construction Period
Dec 2019 to Aug 2020 (270 Days)

Area
3,000 square meters

ON Semiconductor’s head office located at the 18th, 19th and penthouse of One Griffinstone, Filinvest City, Muntinlupa.

Location

One Griffinstone, Filinvest City
Muntinlupa, Metro Manila


DTCC Head Office

Construction Period
Nov 2019 to Jan 2020 (75 Days)

Area
800 square meters

Penthouse of V Corporate Center, renovated with the design of GAYO and the construction services of COREBILT.

Location

V Corporate Center
Makati City, Metro Manila


Forest Lake Head Office

Construction Period
Jul 2019 to Sep 2019 (45 Days)

Area
1200 square meters

Former LANDCO office, completely remodeled with the architecture of ESPASYO and the construction services of COREBILT.

Location

BF Homes
Parañaque City, Metro Manila


Forest Lake San Ildefonso

Construction Period
Apr 2019 to May 2019 (30 Days)

Area
120 square meters

A newly constructed structure, fit-out immediately as the first tenant of the building.

Location

Barangay Sapang Putol
San Ildefonso, Bulacan


Forest Lake Malasiqui

Construction Period
Feb 2019 to Apr 2019 (45 Days)

Area
190 square meters

A large office space occupying the entire 2nd storey of the building.

Location

Malasiqui, Pangasinan


Forest Lake San Leonardo

Construction Period
Feb 2019 to Apr 2019 (45 Days)

Area
160 square meters

An office with a 100 square meter ground floor and a shared second floor that was walled up to separate the company from its neighboring tenant.

Location

Barangay San Vicente
Gapan, Nueva Ecija


Forest Lake San Jose

Construction Period
Aug 2018 to Oct 2018 (45 Days)

Area
260 square meters

An office with a 160 square meter ground floor and a 100 square meter mezzanine floor. Originally meant for a bank, turned into a satellite office.

Location

Barangay Paraiso
San Jose, Nueva Ecija


Forest Lake Koronadal

Construction Period
Jun 2018 to Aug 2018 (45 Days)

Area
110 square meters

Originally the CAP building in Koronadal, turned into a shared building between Forest Lake and CAP with common areas such as the pantry and comfort rooms also renovated.

Location

Barangay Paraiso
Koronadal, South Cotabato


Forest Lake Pozorrubio

Construction Period
Apr 2018 to May 2018 (30 Days)

Area
106 square meters

A former restaurant turned into a long spacious office. This office renovation also involved the new construction of a comfort room within the office.

Location

Barangay Amagbagan
Pozorrubio, Pangasinan


Forest Lake Orani

Construction Period
Oct 2017 to Nov 2017 (30 Days)

Area
96 square meters

The first construction project I managed. This project involved demolition of masonry walls to convert what was originally four 24 square meter commercial units into one seamless office.

Location

Barangay Doña
Orani, Bataan